Albion Chemicals (Pty) Ltd appointed A2V as Project Managers and Engineers for the upgrade to their facility in Paarden Eiland. The project included the following:

  • A new flammable products store for Acetone, Benzine, Turpentine, Methylated Spirits and Thinners. The store included ventilation and foam injection systems design.
  • A new emergency bund facility and increased storage capacity for Sodium hypochlorite and Hydrochloric Acid.
  • Improved loading area drainage and installation of an emergency pump sump and all of the associated pumping equipment.
  • A new bottling facility with improved safety features and process control.
  • Construction of a new workshop and change rooms.
  • A new Fire Protection System and upgraded security system.

A2V were responsible for every aspect of the project from inception:

  • Planning permission and approvals
  • Design and drawings
  • Specification and tenders
  • Appointment, co-ordination and supervision of contractors
  • Final Certifications

The facility upgrade was carried out with the factory in full production, requiring careful planning and co-ordination of activities. It was commissioned in August 2013.